Secondary Aluminum Facility – Chlorine Injection System

Provided the design and construction oversight for a chlorine gas injection system in the cast house of a major aluminum supplier. The system was designed to deliver, control, and inject chlorine gas into aluminum furnaces for removal of impurities. The key elements of the project included:

  • Design and specification of piping, valves, instrumentation, and controls
  • Computation Fluid Dynamic (CFD) Modeling to simulate the consequences of potential chlorine gas leaks to satisfy OSHA compliance requirements
  • Development and implementation of the Process Safety Management Program for the use of chlorine gas in the process